The American Family Insurance construction project features the following:
Overview:
The American Family Insurance Amphitheater construction project will be completed over a two year period. Phase one work includes the demolition of the existing dressing room building, stage, and back of stage support areas. New construction will include a new dressing room building with state-of-the-art amenities for performers and the raising of the current roof to 65 feet, to increase stage production.
The second phase of work will begin immediately after Summerfest 2019. Phase two construction will include new concourses, new restrooms, accessibility enhancements including a new elevator, hospitality areas, and increased food and beverage operations.
Construction Timeline:
Phase 1: Now – June 2019
Phase 2: Post Summerfest 2019 – June 2020
Grand Opening: Summerfest 2020
Project Cost: $50 million
Amphitheater Development Area: 12.5 acres
Amphitheater Seating Capacity: Approximately 23,000
Architects:
Eppstein Uhen Architects
Construction Manager
Hunzinger Construction Company
Consultants:
John Sergi Food and Beverage Hospitality Design
Johnson Controls
Larson Engineering
Legends Food and Beverage
Mid-City Plumbing
SIA Acoustics
Sigma Engineering
Staff Electric
>FOR MORE INFORMATION CONTACT: Julie Dieckelman, (414) 270-6517